Kolkata-based Titagarh Rail Techniques Restricted (TRSL), tasked with producing driverless trains for Bengaluru Metro’s yellow line, is scheduled to ship its first prepare set by the tip of this yr or early subsequent yr. The corporate was anticipated to ship the primary prepare set by August 2024. The 18-km yellow line connects RV Highway to Bommasandra through Digital Metropolis, a key manufacturing and technological hub of Bengaluru.
Talking to indianexpress.com, Prithish Chowdhary, Deputy Managing Director, Titagarh Rail Techniques, stated, “The manufacturing of the primary prepare set at Titagarh Rail Techniques Ltd is nearing completion. Titagarh is targeted on dispatching the primary localised prepare set for the Bangalore Metro 4RS-DM challenge by the tip of December or early January 2025.”
He added, “The trains are at the moment present process rigorous testing at varied stations. These trains are constructed to cater to buyer necessities and comply with stringent high quality requirements. This can mark a major milestone as it is going to be the primary localised stainless-steel trainset produced by Titagarh and CRRC for this challenge.”
Chowdhary additionally stated that following the supply of the primary prepare set, and with the institution of processes, Titagarh will ramp up manufacturing to 2 prepare units per thirty days shortly after the primary prepare set’s supply.
The primary communication-based prepare management system prototype prepare from China was acquired by Bangalore Metro Rail Company Restricted’s Hebbagodi depot on February 14 this yr.
Nevertheless, BMRCL Managing Director Maheshwar Rao was hopeful of beginning operations alongside the yellow line in January 2025 with solely three trains, pending the anticipated supply of prepare units by the tip of December. In October, he stated that BMRCL anticipated the primary prepare from Titagarh by the primary week of December and a second one by the tip of December. Subsequently, with three trains, BMRCL hoped to operationalise the yellow line between the second and final weeks of January.
With the supply of the second prepare set now anticipated by late December or January 2025 and the third prepare set in a phased method, operationalising the yellow line in the course of the second and final weeks of January seems uncertain. “We expect the prepare set to be dispatched earlier than the tip of the yr, per the most recent info. We count on no less than two prepare units from TRSL by the tip of January. Nevertheless, we are going to get a transparent image solely after we maintain a evaluate assembly with TRSL over the manufacturing and supply of the rolling inventory,” Rao stated on Monday.
As a part of the contract settlement signed in December 2019 with BMRCL, Titagarh is answerable for producing 34 of the 36 prepare units wanted for the yellow line. Solely two prepare units, comprising 12 coaches, might be manufactured in China. The manufacturing started on Could 18, 2024, with the primary prepare set initially slated for supply in August 2024. Nevertheless, Titagarh missed the deadline and pushed it to late December 2024.
In December 2019, China’s CRRC Nanjing Puzhen Firm Restricted acquired the contract to provide 2,016 coaches, anticipated to be delivered inside 173 weeks (by Could 2022). Nevertheless, owing to provide chain challenges, CRRC struggled to establish a neighborhood producer in keeping with the 75 per cent native manufacturing requirement below the Make-in-India initiative.
The 18.82-km metro line connecting RV Highway to Bommasandra (Attain 5) is constructed below Section II of the Bangalore metro rail challenge at a price of Rs 5,744 crore. This metro stretch goals to boost connectivity from south Bengaluru to the IT hub in Digital Metropolis, decreasing site visitors congestion at Silk Board Junction and on Hosur Highway.
Why must you purchase our Subscription?
You wish to be the neatest within the room.
You need entry to our award-winning journalism.
You don’t wish to be misled and misinformed.
Select your subscription package deal