The Congress has criticised the PM for this, saying the challenge poses a risk to the Panna Tiger Reserve.
What’s the Ken-Betwa Hyperlink Undertaking (KBLP)?
The KBLP envisages transferring water from the Ken river to the Betwa river, each tributaries of the Yamuna. The Ken-Betwa Hyperlink Canal can be 221 km in size, together with a 2-km tunnel. In accordance with the Jal Shakti Ministry, the challenge is anticipated to offer annual irrigation to 10.62 lakh hectares (8.11 lakh ha in MP and a couple of.51 lakh ha in UP) of land, provide ingesting water to about 62 lakh individuals, and generate 103 MW of hydropower and 27 MW of solar energy.
It’s the first challenge underneath the Nationwide Perspective Plan for interlinking of rivers, which was ready in 1980. This plan has 16 initiatives underneath its peninsular element, together with the KBLP. Other than this, 14 hyperlinks are proposed underneath the Himalayan rivers improvement plan.
The Ken-Betwa Hyperlink Undertaking has two phases. Part-I’ll contain constructing the Daudhan Dam complicated and its subsidiary items such because the Low Degree Tunnel, Excessive Degree Tunnel, Ken-Betwa Hyperlink Canal and energy homes. Part-II will contain three parts — Decrease Orr Dam, Bina Complicated Undertaking and Kotha Barrage.
The Union Cupboard had authorized Rs 44,605 crore (at 2020-21 costs) for the KBLP challenge in December 2021.
On Wednesday, PM Modi is to put the inspiration stone for the Daudhan Dam. Daudhan dam is 2,031 m lengthy, out of which 1,233 metre can be earthen and the remaining 798 m can be of concrete. The peak of the dam can be 77 m. In accordance with the Jal Shakti Ministry, the dam will submerge about 9,000 hectares of land, affecting 10 villages.
Infrastructure firm NCC Ltd has been awarded the contract for the Daudhan Dam.
By when will the challenge be accomplished?
In accordance with the Jal Shakti Ministry, the KBLP challenge is proposed to be carried out in eight years.
When was the Ken-Betwa challenge settlement signed?
On March 22, 2021, a memorandum of settlement was signed among the many Ministry of Jal Shakti and the governments of Madhya Pradesh and Uttar Pradesh to implement the Ken-Betwa Hyperlink Undertaking.
How was the challenge conceptualised?
The concept of linking the Ken with the Betwa received a significant push in August 2005, when a tripartite memorandum of understanding for preparation of an in depth challenge report (DPR) was signed among the many Centre and the 2 states. In 2008, the Centre declared the KBLP a Nationwide Undertaking. Later, it was included as a part of the Prime Minister’s bundle for the event of the drought-prone Bundelkhand area
In April 2009, it was determined that the DPR can be ready in two phases. In 2018, a complete DPR, together with Part-I, II and extra space proposed by Madhya Pradesh, was ready. It was despatched to Uttar Pradesh, Madhya Pradesh and the Central Water Fee in October 2018.
Which areas will profit from it?
The challenge lies in Bundelkhand, which spreads throughout 13 districts of Uttar Pradesh and Madhya Pradesh. In accordance with the Jal Shakti Ministry, the challenge can be of immense profit to the water-starved area, particularly the districts of Panna, Tikamgarh, Chhatarpur, Sagar, Damoh, Datia, Vidisha, Shivpuri and Raisen of Madhya Pradesh, and Banda, Mahoba, Jhansi and Lalitpur of Uttar Pradesh. “It would pave the way in which for extra river interlinking initiatives to make sure that shortage of water doesn’t grow to be an inhibitor for improvement within the nation,” the Ministry mentioned in a press release.
Why must you purchase our Subscription?
You need to be the neatest within the room.
You need entry to our award-winning journalism.
You don’t need to be misled and misinformed.
Select your subscription bundle